08/20Build

Planning & project setup

Sprints · repo · CI/CD

Deliverables
4
Teams
6
RACI activities
5
Templates
4

Goal

Lay the rails before running the train: a baselined plan, repository, automated checks, three separate environments and a reporting rhythm.

Inputs → outputs

Inputs

  • SOW, SRS, SDD
  • Prioritised backlog

Deliverables

  • Baselined project plan + sprint calendar + Definition of Done
  • Repo with README, CONTRIBUTING, .env.example and a green CI pipeline
  • A staging environment the client can open
  • Risk register and communication plan

Teams & roles

  • Project Management / Scrum Masterplan, sprint calendar, risks, communication
  • DevOps / SRECI/CD and environments
  • Engineering (FE · BE · Mobile)repo, branching, project skeleton
  • Quality Assurance (QA/QC)co-designs the Definition of Done
  • Project Management Office (PMO)approves the plan baseline
  • Client (Product Owner / sponsor)appoints the Product Owner, follows the board

RACI matrix

R — does the work · A — accountable, final sign-off (exactly one A per activity) · C — consulted before · I — informed after.

ActivityPMDevQASecOpsInfraPMOClient
Project plan & sprint calendarACC···CC
Definition of DoneARR·····
Repo, branching, PR template·A··C···
CI & dev / staging / production·C·CAR··
Risk register & communication planA·····CI

PM = Project Management / Scrum Master; Dev = Engineering (FE · BE · Mobile); QA = Quality Assurance (QA/QC); Sec = Application Security (AppSec); Ops = DevOps / SRE; Infra = Infrastructure & Network; PMO = Project Management Office (PMO); Client = Client (Product Owner / sponsor)

Quality gate

CI green on main; staging serves an end-to-end "hello world"; plan baselined.

Entry criteria

  • SDD and first-sprint API contract frozen
  • Team and roles confirmed

Exit criteria

  • Baselined plan: scope, schedule, resources, risks
  • Definition of Done agreed
  • CI green on main
  • Staging runs an end-to-end "hello world"
  • Client has access to the work board

Activities

  1. 1.Slice the backlog into 1–2 week sprints, agree a Definition of Done
  2. 2.Create the repo, branch conventions, PR template, protect main
  3. 3.Set up CI: lint, type-check, tests, image build on every PR
  4. 4.Create dev / staging / production, with separated env vars and secrets
  5. 5.Start the risk register, communication plan and weekly report

Checklist

Tick to self-review — 0/5. Ticks stay in this browser only and are not sent anywhere.

Document templates

Markdown (.md) files: open in any editor, or paste into Word / Google Docs. Each states its purpose, who fills it in and when.

Client involvement

  • Appoint one approver (client-side product owner)
  • Get access to the work board to follow progress

Tools

  • GitHub / GitLab
  • GitHub Actions
  • Docker Compose
  • Jira / GitHub Projects / CT Work

Reference standards

The Scrum Guide (2020)
Scrum events, roles and artefacts
The Twelve-Factor App
Config in env, separate build/release/run, dev/prod parity
Conventional Commits 1.0.0
Machine-readable commit message convention
ISO 31000:2018
Risk management — principles and guidelines

Common pitfalls

  • Coding before CI exists → technical debt from day one
  • Sharing a database between staging and production
  • A vague Definition of Done
  • No baseline, so slippage cannot be measured

Real example

cuongthai.com: pushing to main no longer deploys. Both deploy workflows are manual-only because they once raced each other on every push and caused real outages (feed 500s while the schema lagged the image, containers recreated mid-flight). Deploying is a deliberate script, not a side effect of pushing.

Where to learn

Subjects and courses on cuongthai.com that teach this stage’s work.